Load line
Also called Plimsoll mark
Marks on a vessel's hull showing the maximum amidships draft to which she may lawfully be loaded in the circumstances and seasons that apply to her. The best-known mark is the Plimsoll mark.
How it works
A load line is the legal limit on how deep a ship may sit. The marks are painted amidships on both sides. The load line mark is a ring 12 inches in outside diameter, crossed by an 18 inch horizontal line whose upper edge passes through the center of the ring, and it sits below the deck line by the assigned summer freeboard. Other lines on the mark are for different seasons and zones.
Freeboard is the distance that results. The rules measure it vertically down amidships from the upper edge of the deck line to the upper edge of the related load line. The deck line itself is a horizontal line 12 inches long and 1 inch broad, set where the freeboard deck meets the outside of the shell.
The allowed draft changes with the sea, so the line that counts depends on the zone or seasonal area the ship is in. A vessel in fresh water of unit density may submerge the appropriate line by the fresh water allowance on its certificate. The Coast Guard policy notes say it does not in general perform the assigning authority duties itself, and the certificate stays valid only through annual endorsement.
What to know for the exam
- Questions ask how often periodic surveys to renew the load line assignment are made. The answer is five years, because each full term certificate is issued for five years with annual surveys between.
- Another question type asks which party administers the load line regulations for U.S. vessels. The Coast Guard does, even though surveys are delegated to authorized assigning authorities.
- Know that freeboard is measured from the deck line to the load line, and that the load line limits how deep the ship may be loaded.
Common questions
Sources
- 46 CFR 42.01-10, Sec. 42.01-10(a); Plimsoll mark: USCG Load Line Policy Notes, Sec. 146 CFR 42.01-10 on eCFR
- 46 CFR Part 42, Sec. 42.01-10(h) and (i) Freeboard and freeboard deck; Sec. 42.07-15 Zones and seasonal areas; Sec. 42.13-20 Deck line; Sec. 42.13-25 Load line mark46 CFR Part 42 on eCFR
- USCG Load Line Policy Notes, Sec. 5 Administration of Load Lines; Sec. 9 General Load Line RequirementsLoad Line Policy Notes (USCG)
More Stability and Construction terms