The distance from the weather deck to the waterline.

How it works

Freeboard is the vessel's reserve above the water. The Army handbook defines it as the vertical distance from the waterline to the edge of the lowest outside deck and notes it changes with the weight of cargo and provisions. As draft goes up, freeboard goes down by the same amount.

For load line purposes 46 CFR Part 42 makes the measurement exact. The freeboard is measured vertically downward amidships from the upper edge of the deck line to the upper edge of the related load line. The deck line is a horizontal line 12 inches long and 1 inch wide, marked amidships on each side, and its upper edge normally passes through the point where the upper surface of the freeboard deck meets the outer surface of the shell.

The freeboard deck is normally the uppermost complete deck exposed to weather and sea that has permanent means of closing all openings in its weather part, and below which all side openings can be closed watertight. Load line marks then show the maximum amidships draft to which the vessel may be lawfully submerged for the season and circumstances.

What to know for the exam

  • Load line questions ask what freeboard is measured from, and the 46 CFR Part 42 answer is the upper edge of the deck line, not the bulwark, the sheer strake or the gunwale bar.
  • Deck general questions use freeboard in the vessel construction, trim and stability topic together with draft and trim, and in the maritime law and documentation topic, where load line rules decide whether a vessel needs marks.
WORKED EXAMPLE

Freeboard from draft

A barge has her deck edge 9 feet above the bottom. Floating at a 6 ft 6 in draft, her freeboard is 9.0 minus 6.5 = 2.5 feet, or 2 ft 6 in. Loading another 6 inches of draft would leave 2 feet.