The 2026 NMC Backlog: A Timeline of the Coast Guard's Own Estimates

On May 4, 2026, the National Maritime Center reported more than 19,000 submissions waiting. This is every estimate and the key notices it published around the 2026 lapse, in its own words, next to the two lapses before it.

Data through October 2026 (monthly performance reports through August 2025)Source: U.S. Coast Guard National Maritime Center, GAO, DHS OIGLast updated 2026-11-16Data analysis by Mariner IQ

19,000+
Waiting on May 4

"More than 19,000 submissions and growing," the NMC said when it formally resumed services.

3
Estimates in 11 weeks

8 to 12 months, then 8, then 4 (excluding time waiting on the mariner).

30,922
Contacts in August 2026

The NMC Contact Center's busiest month in its 2025 to 2026 chart.

What the NMC said, and when

The NMC closed on February 2, 2026, and issued the same closure notice again on February 17; its later bulletins count cancelled exams from February 17. Through the spring it extended credentials and letters so mariners could keep working, kept its online portal open (apart from an outage reported March 23 and fixed March 24), and on April 22 said its civilian staff had returned "under alternative funding arrangements." It formally resumed services on May 4.

From there, the story is the estimate. Each bulletin below is quoted exactly; hover or tap a dot in the chart, or read the list.

The NMC's published processing estimates, 2026

04812 moFebMarAprMayJunJulAugSepOctLapse: NMC closesClosed againPortal outageStaff backServices resumeExam centers120-day reliefNavita8 to 12 months8 months4 months**excluding time waiting on the mariner
04812 moFebAprJunAugOctLapse: NMC closesServices resume120-day reliefNavita8 to 12 months8 months4 months**excluding time waiting on the mariner
What to notice: The estimate fell from a range of 8 to 12 months to 4 months between May and July, and the 4-month figure leaves out time waiting on the mariner.Source: NMC bulletins, 2026 (listed below).

Download this chart:PNGPNG (2400px)SVG· Free to reuse with the credit line intact.

The key 2026 notices, in the NMC's words

  1. Jan 7, 2026
    System
    Upcoming Launch: New Application Submission Portal and Redesigned Website

    “will officially launch its new online Application Submission and Additional Information Portal (ASAP) and redesigned website on Monday January 26, 2026”

  2. Feb 2, 2026
    Closure
    Lapse in Appropriations and Government Shutdown

    “the National Maritime Center (NMC) and all Regional Examination Centers (RECs) are closed until further notice”

  3. Feb 17, 2026
    Closure
    Lapse in Appropriations and Government Shutdowns

    “the National Maritime Center (NMC) and all Regional Examination Centers (RECs) are closed until further notice”

  4. Mar 19, 2026
    Relief
    Lapse in Appropriations and Government Shutdown UPDATE #2: Mitigation Efforts, Extensions

    “expire between January 1 and April 30, 2026, remain valid until June 30, 2026”

  5. Mar 23, 2026
    System
    Temporary Outage: Application Submission Portal

    “the NMC is unable to accept applications through the portal at this time”

  6. Mar 24, 2026
    System
    Application Submission Portal Restored

    “The portal is now available, and mariners may resume submitting applications and documents.”

  7. Apr 22, 2026
    Relief
    CORRECTED UPDATE #3: Mitigation Efforts, Extensions

    “National Maritime Center (NMC) civilian staff have returned to work under alternative funding arrangements”

  8. May 4, 2026
    Estimate
    Resumption of Services at the National Maritime Center and Regional Examination Centers

    “currently more than 19,000 submissions and growing. Processing timelines are expected to extend 8-12 months from the date a completed application is received.”

  9. May 7, 2026
    Notice
    USPS Shipping Labels and Extended Processing Timelines

    “applications may not be completed for several months after submission”

  10. May 15, 2026
    Resumption
    Resumption of Services at Regional Examination Centers

    “Effective Monday, May 18, 2026, all regional examination centers (RECs) and monitoring units (MUs) except for REC New Orleans and MU San Juan will return to routine operations”

  11. May 26, 2026
    Relief
    NMC Extension Policy Update

    “expire between January 1, 2026, and July 31, 2026, will remain valid through August 31, 2026”

  12. Jun 16, 2026
    Estimate
    NMC Processing Timeline Update

    “complete applications are expected to be processed within 8 months from the date received, an improvement from the previously published estimate of 8-12 months”

  13. Jul 21, 2026
    Estimate
    NMC Processing Timeline Update 2

    “complete applications are expected to be processed within 4 months from the date received, excluding any time waiting for mariner applicants to test or provide additional information”

  14. Aug 27, 2026
    Relief
    CORRECTED Relief for Mariners with Pending MMC Applications

    “A mariner may qualify for a temporary 120-day authorization to continue sailing under the authority of an expired credential”

  15. Sep 11, 2026
    System
    U.S. Coast Guard Navita: Planned Actions for Launch

    “its launch will not immediately reduce current processing timelines”

Three lapses, side by side

The fall 2025 lapse was short: closure on October 1, and exam centers expected back to routine operations from November 24. The FY2019 lapse is the better comparison, because the NMC's monthly reports cover its whole recovery. Applications in process went from 1,801 in December 2018 to 7,712 in March 2019, and net processing time peaked at 32.65 days in June 2019. By September 2019 the pile was back to 1,867, and on August 26, 2019 the NMC said it would resume processing all applications "within the stated goal of 30 net days."

Whether 2026 follows that shape is not something the published numbers can show yet: the 2019 recovery is visible because the monthly reports kept coming, and for 2026 they have not been posted.

Three funding lapses, by NMC notice

Days from each lapse's first closure notice. Hover or tap a dot for the notice.

Day 060120180240FY2019 lapseNotices Dec 2018 to Aug 2019Fall 2025 lapseNotices Oct to Nov 20252026 lapseNotices Feb to Aug 2026
Day 060120180240FY2019 lapse Notices Dec 2018 to Aug 2019Fall 2025 lapse Notices Oct to Nov 20252026 lapse Notices Feb to Aug 2026
What to notice: Each dot is one of the dated NMC notices quoted on this page, counted in days from that lapse's first closure notice.Source: NMC Announcements Archive (FY2019, 2025 and 2026 bulletins).

Download this chart:PNGPNG (2400px)SVG· Free to reuse with the credit line intact.

Show the data
Lapse notices
DateLapseNotice
December 26, 2018FY2019Lapse in Appropriations & Partial Government Shutdown
January 25, 2019FY2019Update 3: Mitigation Efforts Due to Lapse in Fiscal Year 2019 Appropriations
August 26, 2019FY2019Final Update: Fiscal Year 2019 Partial Government Shutdown
October 1, 2025Fall 2025Lapse in Appropriations and Government Shutdown
November 3, 2025Fall 2025Lapse in Appropriations and Government Shutdown UPDATE #3: Mitigation Efforts, Extensions
November 13, 2025Fall 2025Resumption of Services at Regional Examination Centers
February 2, 20262026Lapse in Appropriations and Government Shutdown
February 17, 20262026Lapse in Appropriations and Government Shutdowns
March 19, 20262026Lapse in Appropriations and Government Shutdown UPDATE #2: Mitigation Efforts, Extensions
March 23, 20262026Temporary Outage: Application Submission Portal
March 24, 20262026Application Submission Portal Restored
April 22, 20262026CORRECTED UPDATE #3: Mitigation Efforts, Extensions
May 4, 20262026Resumption of Services at the National Maritime Center and Regional Examination Centers
May 7, 20262026USPS Shipping Labels and Extended Processing Timelines
May 15, 20262026Resumption of Services at Regional Examination Centers
May 26, 20262026NMC Extension Policy Update
June 16, 20262026NMC Processing Timeline Update
July 21, 20262026NMC Processing Timeline Update 2
August 27, 20262026CORRECTED Relief for Mariners with Pending MMC Applications

Applications in process, all printed months

Switch to All years to see the 2019 rise and recovery.

010k20k30kGoal: 9,000 or fewermore than 19,000 (NMC, May 4, 2026)2023202420252026
010k20k30kGoal: 9,000 or fewermore than 19,000 (NMC, May 4, 2026)2023202420252026
What to notice: In 2019 the pile rose for three months after the lapse and was back near its starting point about nine months after the first closure.Source: NMC monthly performance reports; May 4, 2026 bulletin.

The phones tell the story

Another monthly 2026 series the NMC has published is its Contact Center volume. It shows 9,588 contacts in October 2025, when the fall lapse began, rising to 30,922 in August 2026. Contacts do not measure the backlog, but they show how many mariners were checking on applications through the recovery.

NMC Contact Center contacts by month, October 2025 to October 2026

010k20k30k40k10kOct 2514kNov 2519kDec 2523kJan 2622kFeb 2620kMar 2623kApr 2627kMay 2627kJun 2630kJul 2631kAug 2627kSep 2623kOct 26
010k20k30k40k10kOct 2514kNov 2519kDec 2523kJan 2622kFeb 2620kMar 2623kApr 2627kMay 2627kJun 2630kJul 2631kAug 2627kSep 2623kOct 26
What to notice: Monthly Contact Center contacts, as labeled on the NMC's chart.Source: NMC Performance page, "Contact Center: Total Contacts 2025-2026" (values as labeled on the chart).

Download this chart:PNGPNG (2400px)SVG· Free to reuse with the credit line intact.

Show the data
Contact Center contacts
MonthContacts
Oct 259,588
Nov 2513,661
Dec 2519,397
Jan 2623,493
Feb 2622,302
Mar 2619,759
Apr 2623,416
May 2627,096
Jun 2627,156
Jul 2629,911
Aug 2630,922
Sep 2626,695
Oct 2622,649

Frequently asked questions

Sources & data notes

Download the data

nmc-monthly-performance.csv: month, product, metric, value, unit, goal_value, method, source_id, source_url, report_month, page, notes. One row per printed value.

nmc-processing-timeline-2026.csv: date, title, source_url, statement_verbatim, published_estimate_low_months, published_estimate_high_months, excludes, backlog_floor, event_type.

Free to reuse with credit to Mariner IQ (data analysis by mariner iq). The underlying documents are U.S. government works.

  • Monthly values are the figures each NMC report prints for its own month. Months with no archived report are left blank.
  • The most recent monthly report the NMC has published for credentials covers August 2025; for medical certificates, January 2026. Bulletins run through September 11, 2026.
  • Some 2026 figures are labels the NMC printed inside images on its Performance page (for example the calendar-year 2025 summary). They are transcribed as printed and checked twice.

Methodology

Dates are the dates printed on each NMC bulletin; statements are quoted exactly and checked against the source files. The chart of lapses shows only the notices we quote, counted in days from each lapse's first closure notice; it does not show how long the government was closed. Contact Center figures are the values labeled on the NMC's chart. Full tracker methodology.

Spot an error? Email hello@mariner-iq.com or use the contact page, and we will check it against the source and fix it.
Mariner IQ is not affiliated with, endorsed by, or associated with the United States Coast Guard, the National Maritime Center or the Department of Homeland Security. This page summarizes public government documents for planning purposes; it is not legal or licensing advice. Check current NMC guidance before you act.